Environmental Information Announcement

(Summary description)Name of the unit: Jiangyin Huaxi Iron and Steel Co., Ltd.

  • Categories:Announcement
  • Author:
  • Origin:
  • Time of issue:2020-05-26
  • Views:0
Information
1. Basic Information
1. Name of the unit: Jiangyin Huaxi Iron and Steel Co., Ltd.
2. Organization code: 91320281743107044L
3. Legal representative: Yang Yongchang
4. Production address: No. 287, Luhu West Road, Huaxi Industrial Park, Huashi Town, Jiangyin City
5. Contact information: 0510-86216235
6. Main contents, products and scale of production, operation and management services:
Jiangyin Huaxi Iron and Steel Co., Ltd. is mainly composed of sintering, iron making, steel making and oxygen making. It is a joint steel enterprise that produces 1 million tons of billets annually.
Second, sewage information
1. Main pollutants: particulate matter, sulfur dioxide, nitrogen oxides
2. Emission method: Emission after filtering through the dust collector to reach the national emission standard
3. Number and distribution of discharge outlets: sintering plant head desulfurization and denitrification dust removal outlet, sintering plant tail dust removal outlet, sintering plant dust return outlet, sintering plant finished product silo dust removal outlet, sintering plant finished product dust removal outlet Discharge outlets, sintering plant crushing waste gas dust discharge outlets, sintering plant primary ingredient dust removal outlets, sintering plant secondary ingredient dust removal outlets, ironworks supply transfer dust removal outlets, ironworks coke transfer dust removal outlets, ironworks No. 1 and No. 2 dust removal outlets under the trough, No. 1 and No. 2 dust removal outlets in the iron outlet of the ironmaking plant, coal dust preparation and discharge outlets in the ironworks, hot air furnace dust removal outlets in the ironworks, and underground materials in the steelmaking plant Dust discharge outlet of the silo, dust discharge outlet of the high-level silo of the steelmaking plant, dust discharge outlet of the mixed iron furnace of the steelmaking plant, dust discharge outlet of the continuous casting and cutting of the steelmaking plant, hot metal pretreatment dust removal discharge of the steelmaking plant, and the steel furnace converter No. 1 and No. 2 dust removal outlets, steel flue converter secondary flue gas dust removal outlets, and heat power plant waste heat boiler dust removal outlets.
4. Total discharge of major pollutants
The company strictly enforces the emission limits according to the emission permit requirements. In April 2020, the total amount of pollutants discharged by the company met the emission limits required by the Jiangyin City Environmental Protection Bureau. See the table below for the main pollutant compliance status

The total discharge of major pollutants in the enterprise

Year

particulates

SO2

NOx

COD

Ammonia nitrogen

Total index (Ton/year)

Actual emissions (Ton/month)

Total index (Ton/year)

Actual emissions (Ton/month)

Total index (Ton/year)

Actual emissions (Ton/month)

Total index (Ton/year)

Actual emissions (Ton/month)

Total index (Ton/year)

Actual emissions (Ton/month)

2020

April

899.09

9.46

867.03

3.34

1903.31

17.19

63.68

0.218

4.95

0.002

5. Emission concentration:

Exhaust emissions in April 2020

Discharge port name

Emissions name

Execution standard value

Emission concentration

Exceeding standards

Pollutant discharge standards

Sintering plant head desulfurization and dust removal

Particulates

10

1.29

Up to standard

Opinions on promoting the implementation of ultra-low emissions in the iron and steel industry

Sulfur dioxide

35

0.85

Up to standard

Nitrogen oxides

50

28.06

Up to standard

Sinter plant dust removal

Particulates

10

0.68

Up to standard

Dust removal in the sintering plant

Particulates

10

4.8

Up to standard

Opinions on promoting the implementation of ultra-low emissions in the iron and steel industry

Dust removal of finished product silo of sintering plant

Particulates

10

6.2

Up to standard

Dust removal of finished products in sintering plant

Particulates

10

6.5

Up to standard

Dedusting of broken waste gas in sintering plant

Particulates

10

4.6

Up to standard

Primary ingredient dust removal in sintering plant

Particulates

10

5.5

Up to standard

Dedusting of secondary ingredients in sintering plant

Particulates

10

5.7

Up to standard

Iron and steel supply dust removal

Particulates

10

5.5

Up to standard

Coke transfer in ironworks

Particulates

10

5.5

Up to standard

Dust removal from coal powder preparation in ironworks

Particulates

10

5.8

Up to standard

No. 1 dust removal under the trough of ironworks

Particulates

10

2.39

Up to standard

No. 2 dust removal under the trough of ironworks

Particulates

10

3.62

Up to standard

No. 1 dust removal at the iron outlet of the ironworks

Particulates

10

0.94

Up to standard

No. 2 dust removal at the iron outlet of the ironworks

Particulates

10

1.42

Up to standard

Dust removal of hot blast stove in ironworks

Particulates

10

6.8

Up to standard

Opinions on promoting the implementation of ultra-low emissions in the iron and steel industry

Sulfur dioxide

50

15.9

Up to standard

Nitrogen oxides

200

24

Up to standard

Dedusting of underground silo in steel plant

Particulates

10

5.5

Up to standard

Dust removal of high silos in steel mills

Particulates

10

6.3

Up to standard

Dust removal of steel mixing plant

Particulates

10

4.7

Up to standard

Dust removal for continuous casting and cutting in steelworks

Particulates

10

6.2

Up to standard

Pretreatment and dedusting of molten iron in steel mills

Particulates

10

5.7

Up to standard

No. 1 flue gas in converter of steelmaking plant

Particulates

10

7.1

Up to standard

No. 2 flue gas once in converter of steelmaking plant

Particulates

10

6.5

Up to standard

Secondary flue gas dedusting of converter in steelmaking plant

Particulates

10

2.47

Up to standard

Dust removal of waste heat boiler in thermal power plant

Particulates

20

7.7

Up to standard

Boiler air pollutant emission standards

GB13271-2014

Sulfur dioxide

50

16

Up to standard

Nitrogen oxides

150

40

Up to standard

 

Wastewater discharge in April 2020

Wastewater discharge

Emissions name

Execution standard value

Emission concentration

Exceeding standards

Pollutant discharge standards

PH

6-9

7.73

Up to standard

Standards in Table 3 of "Water Pollutant Discharge Standards for Iron and Steel Industry" (DB32/T1072-2007)

Cod

30

14

Up to standard

Petro

1

0.97

Up to standard

Ammonia nitrogen

5

0.12

Up to standard

Total phosphorus

0.5

0.02

Up to standard

Suspended matter

20

6

Up to standard

 

Solid waste in April 2020

 

Production (ton/month)

Comprehensive utilization (ton/month)

Disposal of qualified units (ton/month)

General solid waste

Steel slag

15377.2

15377.2

 

Blast furnace slag

39691.88

39691.88

 

Desulfurized gypsum

3098.92

3098.92

 

Hazardous Waste

Waste mineral oil

0.8

 

 

 

3. Construction and operation of pollution prevention facilities:
 
1. Atmospheric pollutant emission compliance
Huaxi Iron and Steel Co., Ltd. has 3 production branches and raw material yards, specifically divided into: iron making branch (sintering workshop, blast furnace workshop), steel making branch, gas company, raw material yard. The pollutants produced by each branch are mainly smoke, dust, sulfur dioxide, nitrogen oxides, noise, production wastewater and domestic sewage. According to the environmental management regulations, our company treats the pollutants produced by each branch separately, so as not to meet the standards and do not discharge. Specific governance measures are as follows:
Material yard: build a fully enclosed and sealed raw material yard, and install a fixed water spray facility for various raw material piles. The material yard adopts closed treatment in the process of transferring raw materials, and seals the belt corridor to reduce the production of raw materials during loading and unloading The dust is discharged in an unorganized way, and the road is controlled by spraying water to increase the humidity.
Iron plant sintering workshop: The dust generated in the sintering machine batching and crushing process is purified by bag dust removal, and after purification, it is discharged through the chimney. The head of the sintering machine adopts four-field electrostatic dust removal + semi-dry circulating fluidized bed desulfurization + COA coordinated denitrification (dedioxin, heavy metal) device, and the smoke and dust generated by the tail system and the crushing of the finished product use a bag dust collector. Chimney emissions. At the same time, the bagging type dust collector is used for the feeding system of quick lime and lightly burned magnesium powder that are prone to dust, and the dust is collected to enter the sintering batching system for reuse.
Iron plant blast furnace workshop: Each dust-producing point of the blast furnace feeding system uses a closed exhaust hood to collect the dust, and it is purified by a bag-type dust collector. After treatment, it is discharged through the chimney. The blast furnace ore/coking tank upper and lower tank vibrating screens, weighing hoppers, belt conveyors and other receiving points are equipped with a closed exhaust device. The extracted dusty exhaust gas is discharged by the chimney after being purified by the bag filter. When the iron is discharged from the blast furnace, the dust emitted from the iron outlet, iron ditch, slag ditch, swinging flume, etc., adopts the totally enclosed trapping method, and is discharged by the chimney after being purified by the bag filter.
The gas produced by the blast furnace is purified by gravity + bag dust removal system, and the dust concentration after the gas purification is 10mg/m3. In addition to the blast furnace gas for the blast furnace's own use, the rest enters the whole plant gas pipeline network for other users to use. The hot blast stove uses blast furnace gas, and the flue gas containing a small amount of SO2 and NOx after combustion is discharged by the chimney.
Steelmaking plant: the dust produced by the mixing of molten iron in the molten iron furnace is purified by the bag dust collector and discharged through the chimney; the flue gas generated by the hot metal pretreatment is purified by the bag dust collector and discharged through the chimney.
The primary flue gas of converter smelting adopts OG dust removal and purification. The flue gas content of the purified flue gas is ≤10mg/m3, and the flue gas with CO content ≥20% enters the gas cabinet for users to use. When the flue gas CO content<20 % Is discharged into the chimney through a three-way valve to ignite and burn. The secondary flue gas of the converter is discharged through the chimney after being purified by the bag filter.
The dust produced by the converter auxiliary raw material feeding system, underground silo, etc. is collected by the gas collecting hood and then sent to the bag type dust collector for purification, and the exhaust gas is discharged by the chimney after purification.
2. Water pollutant discharge compliance
The drainage system of our company adopts the rain and sewage diversion and decontamination and diversion drainage system, and implements the principles of serial water supply, new replenishment, net replenishment, and recycled water use.
Wastewater pollution production link: The company built a new set of reclaimed water reuse facilities with a daily treatment capacity of 18,000 tons; newly built waste water facility structures of 14,210 square meters and auxiliary buildings of 1,030 square meters. The facility mainly treats various types of production wastewater generated in production, mainly composed of two parts: pretreatment device and advanced treatment device. The pretreatment device uses high-efficiency precipitation, air floatation, and ozone harmless treatment as the main treatment process. After pretreatment The 500t/h effluent enters the circulating water make-up system of the plant for reuse; the pretreated 250t/h effluent enters the advanced treatment device, adopts the treatment process of precision filtration, ultrafiltration and reverse osmosis, and is reused according to the production water quality requirements In the corresponding link of production, part of the concentrated water of the advanced treatment plant is used as the slag flushing and slag water of the steel plant, and part of the concentrated water as wastewater is connected to Jiangyin Huaxi Wastewater Treatment Co., Ltd. for centralized treatment. The implementation of this project can reduce the consumption of fresh water and discharge of water from enterprises, and increase the reuse rate of water.  
3. Noise at the factory boundary
The noise sources of Jiangyin Huaxi Iron and Steel mainly include: sintering cooler, crusher, vibrating screen, blast furnace system, blast furnace blower unit, TRT residual pressure generator unit, hot metal stirring desulfurization station, ferroalloy feeding system, air separation equipment, air compressor and various dust removal Noise generated by fans, pumps and other equipment. Noise control is as follows:
Material yard: The transfer station machinery is set in the building and equipped with vibration reduction measures, and the dust removal fan is equipped with a silencer.
Ironmaking plant sintering workshop: vibration reduction measures are taken for mechanical equipment such as crushing, screening, water pumps; the main exhaust fan is placed indoors, and sound insulation materials are laid on the fan casing; the main exhaust fan, cooling fan, ignition auxiliary combustion fan and some dust removal fans Install mufflers at the exit.
Iron plant blast furnace workshop: Fans of various large-scale dust removal systems are arranged outdoors, mufflers are provided at the outlet of the fan, and sound insulation is wrapped outside the fan casing; vibration damping measures are taken when the fan is arranged on the platform of the transfer station.
Silencers are provided for the suction, exhaust and discharge of the blast furnace blower, and a dedicated blower room is also provided; silencers are provided for the blast furnace cold air vent valve, hot air furnace combustion fan, blast furnace top pressure equalization and pressure relief valve group; gas residual pressure power generation turbine The compressor is equipped with a sound insulation hood; the pulverized coal preparation system ball mill is placed in the building, and various types of pumps are set in special pump rooms.
Steelmaking plant: The noise generated by converter smelting, due to the use of a closed cover, not only strengthens the secondary smoke collection, but also plays the role of sound insulation and noise reduction.
The dust-proof fan casing is wrapped with sound insulation materials, a muffler is provided, the foundation is equipped with vibration reduction, and the inlet and outlet of the fan are softly connected to the pipeline.
Converter vaporization and cooling device steam drum, heat accumulator and deaerator exhaust steam emission are all equipped with muffler; converter, gas pressurizer and various pumps are installed in the building, using the building for sound insulation.
The noise generated by flame cleaning machine and billet cutting adopts building sound insulation.
Public and auxiliary facilities: all kinds of compressors in oxygen station and air compressor station are installed in the building, and mufflers are installed in each gas discharge port.
 
Fourth, the environmental impact assessment of construction projects and other environmental protection administrative licenses:
According to the Suhuan Committee Office [2015] No. 26 "Notice on the Comprehensive Clean-up and Remediation of Environmental Protection and Illegal Construction Projects" and the Chenghuan Committee [2015] No. 23 "About the Issuance of <Jiangyin City Comprehensive Clean-up and Remediation of Environmental Protection and Illegal Construction Projects Work Program "Notice", after being collectively reviewed by the Jiangyin City Environmental Protection Inspection Leading Group, agreed that Jiangyin Huaxi Iron and Steel Co., Ltd.'s annual output of 1 million tons of billet will be included in the "registered batch" and included in daily environmental supervision.
 
Fifth, the emergency plan record registration form:

 

55

 

666

 

6. Environmental self-monitoring plan:

Attachment: Click here to view

Scan the QR code to read on your phone

Jiangyin huaxi steel co.,ltd

Huagang Public Account

Jiangyin huaxi steel co.,ltd

West China Monthly

Jiangyin huaxi steel co.,ltd

Hotline:
0510-8621656186216571
Address: Huaxi Village, Jiangyin City, Jiangsu Province
E-mail:

hxgt@huaxisteel.com

苏ICP备09054839号-1  公安备案号32028102000730
Copyright:Jiangyin huaxi steel co.,ltd  
Powered by www.300.cn